RESIGHT is pleased to announce substantial completion of mass grading in the long-awaited renovation of the planned urban development uses on Springbrook Farm, the former Alcoa Inc. West Plant site. Since the project groundbreaking in April, the project has progressed at a rapid pace including the ongoing road construction, utility infrastructure installation, and site grading in preparation for an urban development consisting of commercial and residential uses.
The first phase of the redevelopment work involves the construction of a landscaped boulevard, including utilities, running slightly over a mile connecting the existing Hunt Road interchange with the signalized intersection at Hall Road and Associates Boulevard. Property on both sides of the new boulevard are available for development
PROJECT FACTS:
- Approximately 300 acres
- 6000 ft. of roadway opening approximately 100 acres for immediate development
- Current project scope: road construction, utility infrastructure installation, and site grading
- Goals: build an urban development consisting of commercial and residential uses